Beevia project status 2026-08-05 → 2026-08-07 Newest first
Pipeline
Zoho board · five repos · four specs
Written by
beevia-refresh
MVP readiness — estimate ≈46% target 2026-09-01 · provisional · 25 days out

Segment width = weight in the MVP definition · fill = build evidence read from the code and screens, not board acceptance and not commit messages. Empty outlines, left to right: international KYC, cross-currency FX, virtual cards, consent — 34 of 100 weight points, all unstarted, two waiting on a partner decision. From the latest frame, 07 Aug 2026 — method and capability table.

03 07 Aug 2026 The sprint ends with nothing in progress and nothing accepted — 78 of 89 items (88%) parked in a status that has never released one. Corrects two faults in the morning edition: stale audit trails, and an un-fetched repo reported as a stalled workstream.
Sprint0702 · closed
MVP est≈46%
In review78 / 89
Median age11d
Done11
API105 + 29
02 06 Aug 2026 The review queue is not a pile-up from this week — it is a backlog that has been accumulating for a month, and nothing has come out of it in 24 hours. Corrects the previous frame's reading of the queue.
Sprint0702 · ends tomorrow
In review74 / 89
Median age14d
Done11
API100 + 29
01 05 Aug 2026 Delivery is healthy. Verification is the bottleneck, and the PRD gap is not closing. Read the queue as new rather than stale — a reading the next frame corrects.
Sprint0702 · 2 days out
In review72 / 89
Median agenot measured
Done11
API100 + 29